From bare slab to screed ready for covering
Eleven steps in which a raw concrete slab becomes a flat, load-bearing surface. This is how IGRO GmbH works.
-
01
Enquiry and survey
You tell us the area, build-up and date. We look at the site or work from your plans: levels, access, standing place for the pump, water and power.
Site visit
-
02
Quotation and programme
You receive a quotation with screed type, strength class, thickness, insulation, edge strips and joints. We agree the laying date with the heating engineer and site management.
written quotation
-
03
Prepare the substrate
The structural slab is cleaned, openings are closed, pipes and cables fixed. We level height differences with a bound fill or a levelling layer.
before laying
-
04
Edge strip and insulation
The edge insulation strip runs without gaps along all walls, columns and door frames. On top we lay thermal and impact sound insulation with staggered joints, tightly butted.
depending on area
-
05
Covering and underfloor heating
The insulation is covered with PE film, the sheets overlapping. With heated screed, the heating engineer now lays the pipes and tests them for leaks.
Acceptance before the screed
-
06
Set the levels
With the rotary laser we transfer the metre mark into every room. So screed level, door connections and transitions fit across the whole floor.
on laying day
-
07
Mix and convey
The screed pump mixes sand, cement and water in front of the building. Compressed air conveys the mortar through the hose into the floor.
continuously during laying
-
08
Place and screed
We spread the mortar, compact it and screed it to laser level with the straightedge.
room by room
-
09
Trowel and joints
The surface is floated and trowelled, on large areas with the power trowel. We cut movement joints in door openings and at bay boundaries following the joint plan.
immediately afterwards
-
10
Dry and heat
Cement screed needs protection from draughts in the first days, then airing in short bursts helps. Heated screed is heated up following a protocol, no earlier than 21 days after laying.
days to weeks
-
11
Readiness for covering and handover
Before the covering comes the CM test. Only once the limit value is met does the area go to the floor layer. You receive the screed documents and, for heated screed, the heating protocol.
after the test is passed
What you prepare as client
- Windows and external doors are fitted, or the openings are sealed tight.
- Internal plaster, electrical and sanitary installation on the floor are finished.
- The heating pipes are pressure-tested, the protocol is available.
- A metre mark is drawn in every room.
- There is space in front of the building for pump, sand and cement. Water is available.
The complete list to tick off is in the guide Preparing the site for screed.
How long does all this take?
The laying itself is quick: the screed for a detached house is usually placed in one working day. The time until covering is set by drying. With the timeline planner you can see for your laying date when the screed is walkable, when heating starts and from when a CM test makes sense.
FAQ
Questions about the process
How long does it take to lay screed?
Laying in a detached house usually takes one working day, two to three days with insulation and preparation. In multi-storey buildings we work floor by floor to the programme.
What must be finished before the screed?
Windows, internal plaster, the services on the structural slab and, with underfloor heating, the pressure-tested heating pipes. In addition, every room needs a metre mark.
Can you lay screed in winter?
Yes, as long as building elements, material and room air stay frost-free. As a rule, 5 °C applies as the lower limit during laying and in the first days after.
Who measures readiness for covering?
The CM test before laying is among the floor layer's duties to check. On request we agree measuring points and date with them.