Timeline planner: drying and heating
When can the screed be walked on? When can the underfloor heating go on? When is a CM test worthwhile? The planner works it out for your laying date.
All dates are guide values for a normal indoor climate. Manufacturers and design may specify other times. Only the CM test decides readiness for covering.
Heating protocol: function heating
| Day | Date | Phase | Flow target | Flow actual | Outside temperature | Signature |
|---|
Function heating in line with DIN EN 1264-4: 3 days at 20 to 25 °C flow temperature, then 4 days at the maximum design temperature. Function heating is not proof of readiness for covering. The data of the screed and heating manufacturers is what counts.
What the planner calculates
- Walkable and lightly loadable: guide values for each screed type
- Function heating: start no earlier than 21 days after laying for cement screed
- Heating protocol with a date for every day, to print and sign
- The point from which a CM test makes sense, based on the rule of thumb
- Residual moisture limit in CM-% for your combination
Limit values for readiness for covering
| Screed | unheated | heated |
|---|---|---|
| Cement screed (CT) | ≤ 2.0 CM-% | ≤ 1.8 CM-% |
| Fast-drying screed | per data sheet | per data sheet |
The values for cement screed come from DIN 18560-1. For fast-drying screed, the limit from the product data sheet applies. Clarify with the floor layer before testing which value applies to your floor covering.
Why the result is only a guide value
The rule of thumb allows one week per centimetre up to 4 cm thickness and two weeks for every further centimetre. In practice, temperature, humidity, ventilation and screed thickness can shift the result by weeks. So the rule is: covering only goes down once the CM test confirms the limit value. The background is explained in the guide Drying time and readiness for covering.
FAQ
Questions about Drying time and heating protocol
How long does 6 cm of screed need to dry?
By the rule of thumb about 8 weeks: one week each for the first 4 cm and two weeks each for the further two centimetres. In poor room conditions it takes longer, with drying heating it takes less. The CM test is what counts.
When can screed be heated?
Function heating starts no earlier than 21 days after laying for cement screed, unless the manufacturer states otherwise.
What goes into a heating protocol?
Screed type and thickness, laying date, start of heating, the flow temperature for each day, the end of heating, and the date and signatures. The planner produces the table with your data.