Timeline planner: drying and heating

When can the screed be walked on? When can the underfloor heating go on? When is a CM test worthwhile? The planner works it out for your laying date.

Screed type
Limit value for readiness for covering… CM-%

    All dates are guide values for a normal indoor climate. Manufacturers and design may specify other times. Only the CM test decides readiness for covering.

    Enquire with these values

    Heating protocol: function heating

    DayDatePhaseFlow targetFlow actualOutside temperatureSignature

    Function heating in line with DIN EN 1264-4: 3 days at 20 to 25 °C flow temperature, then 4 days at the maximum design temperature. Function heating is not proof of readiness for covering. The data of the screed and heating manufacturers is what counts.

    Date, signature of heating engineerDate, signature of client / site management

    What the planner calculates

    Limit values for readiness for covering

    Screedunheatedheated
    Cement screed (CT)≤ 2.0 CM-%≤ 1.8 CM-%
    Fast-drying screedper data sheetper data sheet

    The values for cement screed come from DIN 18560-1. For fast-drying screed, the limit from the product data sheet applies. Clarify with the floor layer before testing which value applies to your floor covering.

    Why the result is only a guide value

    The rule of thumb allows one week per centimetre up to 4 cm thickness and two weeks for every further centimetre. In practice, temperature, humidity, ventilation and screed thickness can shift the result by weeks. So the rule is: covering only goes down once the CM test confirms the limit value. The background is explained in the guide Drying time and readiness for covering.

    FAQ

    Questions about Drying time and heating protocol

    How long does 6 cm of screed need to dry?

    By the rule of thumb about 8 weeks: one week each for the first 4 cm and two weeks each for the further two centimetres. In poor room conditions it takes longer, with drying heating it takes less. The CM test is what counts.

    When can screed be heated?

    Function heating starts no earlier than 21 days after laying for cement screed, unless the manufacturer states otherwise.

    What goes into a heating protocol?

    Screed type and thickness, laying date, start of heating, the flow temperature for each day, the end of heating, and the date and signatures. The planner produces the table with your data.

    Calculators

    More calculators

    Quote

    Screed planned? Let's talk.

    Tell us the area, screed type and desired date. You will receive a clear quotation.