Drying time and readiness for covering of screed

Walkable is not loadable, and loadable is not ready for covering. Anyone who mixes up these three points in time risks damage to the floor covering.

CM test device with pressure bottle and gauge for measuring residual moisture
In short

Cement screed is walkable after about 3 days, lightly loadable after about a week and fully loadable after about 28 days. Up to readiness for covering, the rule of thumb is one week per centimetre of thickness up to 4 cm and two weeks for every further centimetre. The CM test is what decides: cement screed at most 2.0 CM-%, heated 1.8 CM-%.

Three points in time to tell apart

Point in timeCement screedFast-drying screed
Walkableafter approx. 3 daysafter hours to 1 day, depending on product
Lightly loadableafter approx. 7 daysafter approx. 2 days
Fully loadableafter approx. 28 daysafter approx. 7 days, depending on product
Ready for coveringat ≤ 2.0 CM-% (heated 1.8)limit per data sheet

The times are guide values. The manufacturer's data for the product in question is what counts.

The rule of thumb and its limits

One week per centimetre up to 4 cm, above that two weeks per centimetre: for 6 cm of cement screed that makes about 8 weeks. The rule assumes about 20 °C, normal humidity and regular ventilation. In a cold, damp shell it takes much longer. Thick screeds dry disproportionately slowly, because the water has to travel from deep down through the whole layer.

How the CM test works

For the CM test, a sample is taken at the dampest spot over the full cross-section of the screed, crushed and weighed. The sample goes into a pressure bottle with steel balls and an ampoule of calcium carbide. When shaken, the ampoule breaks and the carbide reacts with the water in the sample to form gas. The pressure on the gauge shows the water content in CM-%. The CM test is the method recognised on site. Electronic meters serve only for a preliminary check.

Ventilating correctly

  • Cement screed: in the first days protect it from draughts and from drying out too fast.
  • Heated screed: the heating stays off until function heating.
  • Airing in short bursts several times a day works better than windows left tilted all the time.
  • Do not store films, boards or stacks of material on the area: nothing dries underneath.
  • Use dehumidifiers only after the initial phase, and keep the rooms closed while doing so.

Speeding up drying

With heated screed, drying heating shortens the wait, see Heating screed up. If the deadline is tight from the start, fast-drying screed is the plannable solution. The timeline planner calculates dates for your laying date.

As of 25 November 2026. The information is general technical guidance. It replaces neither the design nor the manufacturers' data for your project.

FAQ

Frequently asked questions

Can screed keep drying under tiles?

Hardly. A dense covering locks the moisture in. If covered too early, residual moisture can damage adhesive, parquet or waterproofing. That is why testing is done before covering.

Can screed dry too fast?

Yes. Draughts, fan heaters or direct sun in the first days dry the surface faster than the core. With cement screed that leads to cracks and curling of the edges.

How much residual moisture may screed have?

Cement screed at most 2.0 CM-%, heated 1.8 CM-%. For fast-drying screed the value from the product data sheet applies. Some coverings need stricter values, so agree this with the floor layer in advance.