Screed in Germany: a guide for international clients and contractors

Working on a German project and meeting terms such as Estrich, CT-C25-F4 or Belegreife? This guide translates the key words and shows how a German screed job runs.

Screed layer smoothing a large screed area with a power trowel in a commercial building
In short

Estrich is the German word for screed: a mortar layer laid on a structural slab or on insulation, which levels the floor, spreads loads and carries the floor covering. The most common type is cement screed (CT). German screed work follows DIN 18560 and DIN EN 13813, and the CM test decides when the floor can be covered.

German screed terms and their English equivalents

German termEnglish equivalentMeaning
EstrichScreedMortar layer that levels the floor and carries the covering
Zementestrich (CT)Cement screedMoisture-resistant, universal
SchnellestrichFast-drying screedReady for covering after days instead of weeks
HeizestrichHeated screedFloating screed over underfloor heating
Schwimmender EstrichFloating screedOn insulation, with no firm contact to wall and slab
VerbundestrichBonded screedFirmly bonded to the structural slab
BelegreifeReadiness for coveringDry enough to lay the floor covering
MeterrissMetre mark (datum line)Wall mark one metre above the planned finished floor level

More terms, each with its German word, are in the glossary.

How to read CT-C25-F4

The designation under DIN EN 13813 names the binder first: CT is cement screed. C25 is the compressive strength class with 25 N/mm², and F4 is the flexural strength class with 4 N/mm². For floating screed, flexural strength is the decisive figure.

The standards you will meet

  • DIN 18560: screeds in building. Part 2 covers floating screed and heated screed, part 3 bonded screed, part 4 screed on a separating layer and part 7 heavy-duty screed.
  • DIN EN 13813: screed materials and their designation, such as CT-C25-F4.
  • DIN 18202: tolerances in building, which set how flat a screed area must be.
  • DIN EN 1264-4: underfloor heating, including function heating.

Who does what on a German site

  • The screed layer lays the insulation, edge insulation strip, separating layer and the screed itself.
  • The heating engineer lays the pipes, pressure-tests them and runs the function heating.
  • The floor layer carries out the CM test before covering.

Key numbers

ItemCement screed (CT)
Nominal thickness, floating (also the pipe cover for heated screed)45 mm (CT-F4)
Walkableafter about 3 days
Function heating, earliestday 21
Readiness for covering2.0 CM-% (heated 1.8)

Function heating runs for 3 days at 20 to 25 °C, then 4 days at the maximum design temperature. It is not proof of readiness for covering. The timeline planner works out the dates, and heated screed explains the build-up.

What to send for a quotation

  • Area in m², ideally per floor
  • Planned build-up: insulation, screed thickness, underfloor heating yes or no
  • Screed type, if already fixed
  • Site location and floor level
  • Desired date and the progress of the preceding trades
  • Plans or photos, if available

IGRO GmbH works as a subcontractor for general contractors in Hamburg and the surrounding region. Details of the steps are on the page Process. To start, use the contact page.

As of 25 November 2026. The information is general technical guidance. It replaces neither the design nor the manufacturers' data for your project.

FAQ

Frequently asked questions

What does Estrich mean?

Estrich is the German word for screed. It is a layer of mortar laid on a structural slab or on insulation. It levels heights, spreads loads and carries the floor covering.

Which screed types do I meet on German projects?

Mostly cement screed (CT), and fast-drying screed (Schnellestrich) where the schedule is tight. By construction method there are floating screed, bonded screed (Verbundestrich) and heated screed (Heizestrich).

Does IGRO GmbH work for general contractors?

Yes. IGRO GmbH works as a subcontractor for general contractors in Hamburg and the surrounding region, quoting from the bill of quantities and agreeing sections and dates with site management.