Heating heated screed up correctly

Heated too early or too fast, the screed cracks. Not heated at all, the floor layer refuses the job. Here is how to do it right.

Red heating pipes of an underfloor heating system on system boards, with screed being placed behind
In short

Heated screed is heated in two steps before covering. Function heating under DIN EN 1264-4 starts no earlier than 21 days after laying for cement screed: 3 days at 20 to 25 °C flow temperature, then 4 days at the maximum design temperature. Drying heating then dries the screed down to the limit value.

Step 1: function heating

PhaseDurationFlow temperature
Heating up3 days20 to 25 °C
Maximum temperature4 daysmaximum design temperature of the heating
Reducingafterwardsstep by step back down

Function heating shows that the heating works and relieves stress in the screed. It is carried out and recorded by the heating engineer. It is not proof of readiness for covering.

When may it start?

For cement screed no earlier than 21 days after laying. For screeds with additives and for fast-drying screeds, the manufacturers state their own, often shorter periods. Before that point the heating stays off.

Step 2: drying heating

If there is not enough time for natural drying, drying heating follows. The flow temperature is raised in stages following the protocol of the screed or floor covering manufacturer, held for several days and lowered again. Meanwhile the building is ventilated regularly so the moisture leaves it. The CM test comes at the end.

What belongs in the heating protocol

  • Project, screed type, thickness and laying date
  • Start of heating and flow temperature for each day
  • End of heating and condition of the area
  • Date and signatures of heating engineer and client or site management

The timeline planner produces a protocol with the data for your project, which you can print out.

Common mistakes

  • Heating before the waiting time is over.
  • Jumping from cold to full temperature without a heating-up phase.
  • Closed windows: the moisture stays in the room.
  • Areas covered by material, films or cartons.
  • Laying the covering without waiting for the CM test.

As of 25 November 2026. The information is general technical guidance. It replaces neither the design nor the manufacturers' data for your project.

FAQ

Frequently asked questions

What temperature is screed heated to?

For function heating, first 3 days at 20 to 25 °C flow temperature, then 4 days at the maximum design temperature of the system. The screed itself should not exceed 55 °C.

Who is responsible for heating up?

The heating engineer carries out function heating and records it. Drying heating is agreed between client, heating engineer and floor layer.

Does screed always have to be heated up?

Only heated screed. For screed with underfloor heating, function heating is part of the construction sequence. Unheated screed dries in the air.

Guides

More guides

Quote

Screed planned? Let's talk.

Tell us the area, screed type and desired date. You will receive a clear quotation.