Before the screed, windows must be fitted, internal plaster and services on the structural slab finished, and the heating pipes pressure-tested. Every room needs a metre mark. In front of the building, the screed pump needs a standing place with access and a water connection. During laying and in the first days after, the building must be at least 5 °C.
Shell and fit-out
- Windows and external doors are fitted, or the openings are sealed tight.
- Internal plaster is finished and taken down to the structural slab.
- Electrical cables and pipes on the slab are laid and fixed.
- Openings through the slab and chases are closed.
- The structural slab is swept clean, dry and free of material.
Levels and design
- A metre mark is drawn in every room.
- Finished floor level, covering thicknesses and door heights are set.
- The joint plan is available and coordinated with the heating circuits.
- Screed type, strength class and thickness are fixed.
With underfloor heating
- The heating pipes are fully laid and fixed.
- The pressure test is passed and the protocol is available.
- The pipes stay filled and under pressure during laying.
Space for the pump
- Standing place for the trailer as close to the building as possible.
- Space for sand and cement pallets next to it.
- Access for delivery, with a no-waiting zone if needed.
- Water connection within reach.
- A clear route for the hose through a door, window or stairwell.
On laying day and after
- On laying day no other trades work on the areas.
- The building is at least 5 °C, including the nights after.
- The fresh screed is not walked on until we release it.
- No draughts in the first days, then ventilate regularly in short bursts.
- Store nothing on the area until readiness for covering is reached.
What happens next is shown on the page Process and in the guide Drying time and readiness for covering.
As of 25 November 2026. The information is general technical guidance. It replaces neither the design nor the manufacturers' data for your project.