FAQ
Questions and answers about screed
The questions asked most often online and on site. Every answer in a few sentences, with figures instead of platitudes.
Cost and quotation
What does screed cost per m²?
The market guide values for Germany in 2026, including laying, are about €20 to €35 for cement screed and €30 to €50 for fast-drying screed. Insulation and underfloor heating come on top. Details in the guide Screed cost per m².
What information does a screed contractor need for a quotation?
The area in m², the planned build-up with insulation and screed thickness, the screed type, whether there is underfloor heating, the floor level and the desired date. Plans or photos help.
Which trade lays the screed?
The screed layer. They usually also lay the insulation, edge insulation strip and film. The heating pipes are laid by the heating engineer, the covering by the floor layer or tiler.
Can I lay screed myself?
Small areas with bagged material are doable for practised DIYers. For whole flats, floating screed and heated screed, level, flatness, compaction and joints all matter. Mistakes show only later and are expensive.
Drying and readiness for covering
How long must you stay off screed?
Cement screed about 3 days. After that walk on it carefully and put nothing down yet. The manufacturer's data applies.
How often and for how long should you ventilate after screeding?
After the initial phase, air in short bursts several times a day for a few minutes, over weeks. Windows left tilted all the time achieve little. With cement screed, avoid draughts in the first days.
Can screed dry without heating?
Yes. Screed dries in the air if temperature and ventilation are right. In winter, in an unheated shell, it takes very long. Dehumidifiers or a site heater then help.
When can you tile on screed?
When the CM test confirms the limit value: for cement screed at most 2.0 CM-%, heated 1.8 CM-%. Some adhesive and waterproofing systems allow earlier laying on cement screed. The tiler decides that according to the manufacturer's data.
Can screed go mouldy?
The screed itself is mineral and does not go mouldy. But the moisture it releases can lead to mould on cold walls, on insulation or on timber if the building is not ventilated.
Thickness and build-up
How thick must screed be at minimum?
Floating in housing at least 45 mm as cement screed CT-F4. With underfloor heating the figure applies over the pipe. More in the guide Screed thickness and build-up.
Why screed and not simply concrete?
The concrete slab carries the building but is neither flat enough nor insulated. The screed creates the flat surface for the covering, takes the insulation and heating, and improves sound insulation.
Does screed need priming?
Before levelling compound, adhesive or waterproofing, as a rule yes. The primer binds dust, regulates absorbency and improves adhesion.
Does screed have to be sanded?
As a rule not. It is sanded only when the surface is dirty or when the floor layer requires it for the covering.
Underfloor heating
Does screed with underfloor heating have to be heated up?
Yes. Function heating under DIN EN 1264-4 is part of the construction sequence and is recorded. How it runs is explained in the guide Heating screed up.
Is heated screed a screed type of its own?
No. Heated screed describes the construction method with underfloor heating. We lay it as cement screed, and as fast-drying screed when the schedule is tight.
How strong is screed over underfloor heating?
With the right thickness, just as strong as without heating. That is why nominal thickness is measured over the pipe. For living spaces with imposed loads up to 2 kN/m², 45 mm of cement screed CT-F4 over the pipe is enough.
Can underfloor heating be milled into the screed afterwards?
Yes, channels for heating pipes can be milled into load-bearing cement screed of sufficient thickness. This is a trade of its own. Whether the existing screed is suitable is checked beforehand.
Types and properties
Which types of screed are there?
By binder: cement screed, mastic asphalt, synthetic resin and magnesite screed, plus dry screed made of boards. By construction method: bonded screed, unbonded screed on a separating layer, floating screed and heated screed. Overview in the guide Screed types compared.
Is screed waterproof?
No. Cement screed is moisture-resistant but not watertight. In wet rooms, waterproofing belongs under the covering.
What is the difference between screed and concrete?
Both consist of cement, aggregate and water. Screed has a finer grain, mostly up to 8 mm, is laid in thin layers and does not carry the building but the floor covering.
Can screed sink?
Yes, if the insulation below is too soft or not laid over the full area, or if voids remain. Carefully laid, pressure-resistant insulation prevents that.
How much does screed weigh?
Cement screed about 2,100 kg per m³, so roughly 21 kg per m² and centimetre of thickness. The quantity calculator works it out for your area.
Process and site
What should you watch for with screed?
Before laying: finished plaster, closed windows, tested heating pipes, metre mark. Afterwards: do not walk on it, ventilate properly, heat heated screed up following the protocol and cover only after the CM test. Checklist in the guide Preparing the site.
At what temperature can screed be laid?
As a rule from 5 °C building element and air temperature, during laying and in the first days after. Frost and strong heat damage fresh screed.
How much screed can be laid in one day?
That depends on screed type, thickness, floor level and layout. The screed for a detached house is usually laid in one working day.
Does IGRO also lay small areas?
Yes. Call 040 28573297 and tell us the area and the place. We will tell you openly whether and when we can take it on.